CEO: digitalization of the Popayán main substation

How Axon Group took the main transmission substation in Cauca from conventional infrastructure to a fully digital architecture under IEC 61850.

  • ClientCEO
  • CountryColombia
  • SectorSubstations
  • SolutionsAG Projects · AG Builder3
The story in 30 seconds

Challenge, solution, and result

The challenge

Modernize the Popayán main substation, the main point of the Cauca transmission system, to strengthen the reliability and security of the regional power system.

The solution

Transition from conventional infrastructure to a digital IEC 61850 architecture: engineering, panels, FAT, SAT, and AG Builder3 SCADA.

The result

Seven 115 kV bays and 13.2 kV cells in service, monitored and controlled in real time from a single interface.

The challenge

From a conventional substation to a fully digital one

In line with its commitment to strengthen the reliability and security of the regional power system, Compañía Energética de Occidente (CEO, a Colombian utility) undertook the comprehensive modernization of the Popayán main substation, the main point of the transmission system in the department of Cauca.

The challenge was to take the substation from conventional infrastructure to a fully digital architecture under the IEC 61850 standard, in a main bus plus transfer bus topology with voltage levels of 115, 34.5, and 13.2 kV.

  • ClientCompañía Energética de Occidente
  • LocationPopayán, Cauca
  • TopologyMain bus plus transfer bus
Digital marshalling panels installed in the switchyard of the Popayán main substation
Popayán main substation
The solution

How Axon Group digitalized the main substation

  1. Engineering

    From site survey to detailed design

    Technical site survey and basic and detailed engineering of the new digital IEC 61850 architecture.

  2. Panels

    Construction, FAT, and SAT

    Construction and integration of station auxiliary systems, protection, metering, communications, and digital marshalling panels, with complete factory assembly (FAT) and field commissioning (SAT).

  3. SCADA

    Monitoring with AG Builder3

    AG Builder3 SCADA centralizes signals from multiple IEDs and simplifies testing, maintenance, and operation from an intuitive HMI.

Results

The impact on operations

7 baysAt 115 kV and 13.2 kV cells placed in service
IEC 61850Fully digital architecture
Real timeMonitoring, control, and analysis of the entire substation
More stories

Other projects with Axon Group

  • GenerationCO

    Urrá hydropower plant

    SCADA modernization at a 340 MW power plant

    New AG Builder3 SCADA and AG Exchange gateways with Hot-Standby redundancy.

    • AG Builder3
    • AG Exchange
    • Hot-Standby
  • GenerationCO

    CHEC · EPM Group

    Fault diagnosis with AG Comtrade

    Automatic collection of protection relay records to analyze every fault on the network.

    • AG Comtrade
    • COMTRADE
    • Protection
  • InfrastructurePA

    Celmec · Tocumen Airport

    Terminal 2 power system automation

    Remote control from the control room, load shedding and reconnection, and a redundant control network.

    • AG Builder3
    • AG Exchange
    • Redundant networks

Do you want to digitalize your substation?

Tell us about your project and an AG specialist will guide you.