EPM: remote management and monitoring of 17 power plants

The scale of the project pointed to at least a year of work. Axon Group delivered it in a record time of 3 months.

  • ClientEPM
  • CountryColombia
  • Timeline2012
  • ProductsAG Builder3 · AG Exchange
The story in 30 seconds

Challenge, solution, and result

The challenge

Remotely monitor EPM's 17 power plants by integrating 260 relays, a project forecast to take at least a year.

The solution

License and configuration of AG Builder3 SCADA for 15,000 tags and 5 remote clients, with a serial server, an AG Exchange gateway, and engineering.

The result

About 75% less time, lower long-term costs, and an EPM team that now configures the software on its own.

The challenge

Seventeen power plants, one monitoring system

The project covered the integration of 260 relays distributed across EPM's 17 power plants, with the supply of the license and the configuration of AG Builder3 SCADA with 5 clients.

Given its scale, a minimum of 1 year of work was forecast. AG Builder3 makes it easy to build applications, which made it possible to deliver the project in a record time of 3 months.

  • ClientEPM · Colombia
  • Scope260 relays at 17 power plants
  • License15,000 tags · 5 remote clients
Remote monitoring of the power plants
The solution

How Axon Group connected the 17 power plants

  1. Integration

    260 relays in a single system

    The relays of the 17 power plants were integrated using a serial server and the AG Exchange communications gateway.

  2. SCADA

    AG Builder3 for 15,000 tags

    The AG Builder3 license for 15,000 tags and 5 remote clients was supplied and configured, together with the project engineering.

  3. Autonomy

    Software that EPM masters

    Learning it proved easy and intuitive: today EPM no longer hires engineering services to configure or modify the software and only buys the licenses.

Results

The impact on operations

~75%Less execution time
3 monthsInstead of the minimum projected year
15,000Tags in AG Builder3

17 power plants

  • Porce II
  • Porce III
  • Guatapé
  • La Sierra
  • La Tasajera
  • Guadalupe III and El Salto substation
  • Guadalupe IV
  • Playas
  • Troneras
  • La Herradura
  • Jepirachi
  • Sonsón I
  • Sonsón II
  • La Vuelta
  • Pajarito
  • Ayurá
  • Grande
More stories

Other projects with Axon Group

  • GenerationCO

    J.E. Jaimes · Trina Solar

    Connection of the Bosques Solares de los Llanos project

    More than 50 MW of photovoltaic capacity connected to the national power system in 7 months.

    • SIPROTEC 5
    • IEC 61850
    • IEC 60870-5-104
  • SubstationsCO

    EBSA

    Modernization and automation of the Donato substation

    115 kV substation with redundant AG Exchange data concentrators and AG Builder3 HMI.

    • AG Exchange
    • AG Builder3
    • FAT · SAT
  • SubstationsCO

    CEO · Compañía Energética de Occidente

    Digitalization of the Popayán main substation

    From conventional infrastructure to a 115 kV digital IEC 61850 substation.

    • IEC 61850
    • AG Builder3
    • FAT · SAT

Do you want to monitor your power plants from a single place?

Tell us about your project and an AG specialist will guide you.